A data center is a physical facility that houses computing equipment used to store, process and transmit digital information. Its electricity profile depends on the type of facility, its computing load, cooling systems, redundancy design and how continuously it operates.
It is how much electrical demand the facility can place on the system, how consistently it draws power, where it connects, what upgrades are needed and who is contractually responsible for those costs.
Different facilities, different loads
Data centers are not one uniform category. The Delaware Division of Legislative Services’ January 2026 research report describes enterprise, colocation, edge, modular and hyperscale facilities. A small edge site and a multi-building hyperscale campus can have very different power, land, water and transmission requirements.
| Facility type | Typical role | What to investigate |
|---|---|---|
| Enterprise | Computing for one organization | Internal demand, redundancy and expansion plans |
| Colocation | Space and power rented to multiple customers | Tenant load, contracted capacity and phased occupancy |
| Edge | Smaller sites close to users or devices | Local distribution constraints and cumulative sites |
| Modular | Prefabricated or containerized computing blocks | Rapid deployment, generator and cooling footprint |
| Hyperscale | Very large cloud or compute campuses | Transmission, generation, water and multi-phase growth |
Why electricity demand matters
Large data centers can operate at high utilization for long periods. A facility’s peak demand describes the highest draw at a point in time; its load factor compares average demand with peak demand over a period. A high load factor means the facility uses a large share of its peak capacity consistently.
That distinction matters because grid planning is shaped by both maximum demand and duration. A project can create the need for substations, feeders, transmission upgrades, capacity procurement or emergency operating procedures before it uses every megawatt it has requested.
Conceptual illustration only. It does not represent an actual customer or utility load curve.
Cooling, water and backup generation
Electricity is only one part of a data center’s physical footprint. Cooling technology determines how heat is rejected; water may be used directly in some cooling systems or indirectly through the electricity supply chain. Backup generators support continuity during outages but can create local emissions and noise concerns when tested or operated.
Those impacts are site-specific. Water source, withdrawal permits, wastewater capacity, generator type, fuel storage, operating hours, air permits and acoustic studies should be read from the project record—not inferred from the label “data center.”
Why Delaware created a large-load framework
In 2026, Delaware enacted separate rules for large energy-use facilities. The package addresses utility cost allocation, interconnection agreements, power procurement, curtailment, customer protections and public disclosure. The laws do not mean every data center is automatically subject to every provision: the applicable statutory definition, service provider, facility status and date of interconnection matter.
Start with the large-load rules explainer and the bill tracker.
A practical project checklist
- Demand: requested MW, peak MW, annual energy, load factor and ramp schedule.
- Connection: point of interconnection, substation and feeder work, transmission constraints and who pays.
- Power supply: energy supplier, generation contracts, clean-energy qualification and backup strategy.
- Water and land: water source, cooling design, stormwater, wetlands, acreage and zoning.
- Local effects: noise, generator emissions, traffic, construction, jobs and tax arrangements.
- Exit risk: contract length, collateral, minimum bills, cancellation terms and stranded infrastructure.
Capacity is not the same as electricity consumed
Data-center announcements often emphasize megawatts because that is the scale of the electrical connection or peak demand being discussed. But megawatts and megawatt-hours answer different questions. A 100-MW load operating continuously for one hour would use 100 MWh. Operating at that level around the clock for a year would use roughly 876,000 MWh, before accounting for changes in load or downtime. That is an illustration, not an estimate for any Delaware project.
| Measure | Question it answers | What to verify |
|---|---|---|
| Requested capacity (MW) | How much service is the project asking the grid to make available? | Utility application, interconnection request and phase schedule. |
| Peak demand (MW) | What is the highest expected instantaneous draw? | Engineering load forecast and operating assumptions. |
| Annual energy (MWh) | How much electricity is expected to be used over a year? | Annual operating profile and projected utilization. |
| Load factor | How continuously does the facility use power relative to its peak? | Average-to-peak demand over the stated period. |
| Power usage effectiveness (PUE) | How much total facility energy is used relative to IT equipment energy? | Definition, measurement period and design versus operating value. |
A 100-MW interconnection request is not proof that a project is currently consuming 100 MW. Nor does a proposed campus size establish the load that will actually appear on the system. Construction phases, tenant commitments, equipment procurement, cooling design and server utilization all affect the eventual load curve. The public record should distinguish requested, approved, energized, contracted and measured demand.
How a large facility reaches the grid
Before a data center can operate, the developer and relevant utility must work through a sequence of site, service and grid questions. The sequence varies with the project and its point of connection, but it commonly involves:
- Site control and land-use review. Ownership or options, zoning, subdivision, building permits, wetlands and stormwater constraints.
- Utility service study. The local distribution utility evaluates load timing, point of connection, substations, feeders and required distribution upgrades.
- Regional transmission review. PJM and, where applicable, FERC processes address regional transmission, wholesale-market and interconnection issues.
- Supply and capacity arrangements. The customer, utility and suppliers resolve energy supply, capacity exposure, contracts and applicable large-load requirements.
- Construction and energization. Equipment, substations and lines are built, tested and placed in service in stages; the connected load may ramp over time.
A project can have local land-use approval but still lack a final utility service agreement or completed transmission work. Conversely, an interconnection queue entry is not a land-use approval or a commitment to build. Each status belongs to a different process and should be reported separately.
Sources
- Exploring the Data Center Industry in the United States: Identified Impacts & Public Policy Considerations (January 2026)Delaware Division of Legislative Services · January 2026
- Title 30, § 2010 — definitions, including large energy use facilityDelaware Code Online · Current code
- Title 26, § 203G — electric service agreements for large energy use facilitiesDelaware Code Online · Current code
- Title 29, § 8066 — large energy use facilitiesDelaware Code Online · Current code
- PJM — What We DoPJM Interconnection · Regional grid and wholesale-market responsibilities