Nuclear power is part of Delaware’s longer-term energy discussion because it can provide large amounts of firm, low-carbon electricity. The state has completed a feasibility review, but it has not selected a site, authorized a reactor or committed customers to a nuclear project.
The General Assembly’s task-force record lists the report as received July 27, 2026. The report process creates a basis for further evaluation; it does not authorize construction or establish that any particular site is suitable.
What Delaware studied
Senate Concurrent Resolution 18 created the Delaware Nuclear Energy Feasibility Task Force. The task force was directed to examine technical and logistical feasibility, possible locations and infrastructure requirements, economics, regulation, reliability and environmental considerations. SCR 129 later extended the reporting timeline. The General Assembly’s record lists the final report as received July 27, 2026.
Delaware Public Media’s August 12, 2026 reporting on the report says a small modular reactor could take roughly seven to nine years to become operational if the state began the process then, and describes local-government engagement as a key next step. That is a reported planning horizon, not a construction schedule or commitment.
What nuclear could contribute
A nuclear plant can produce electricity continuously and is not dependent on sunlight or wind conditions. In a portfolio, firm nuclear generation could complement solar, wind, storage, demand response and gas-fired generation. It could diversify fuel exposure and contribute to low-carbon electricity supply once operating.
Those potential benefits are system-dependent. A reactor outage still requires reserves; generation must be connected through adequate transmission; a plant may not be located near the load it serves; and the financing and construction period can be long. Nuclear is not an immediate fix for near-term capacity or distribution bottlenecks.
Small modular reactors and conventional nuclear
Small modular reactors are proposed reactor designs intended to use smaller modules and, in some concepts, factory fabrication. “Small” does not mean simple or automatically inexpensive. Commercial costs, licensing timelines, supply-chain readiness, financing terms and operating experience remain material questions for any first deployment.
A conventional large reactor and an SMR are not interchangeable options. Their output scale, cooling requirements, site footprint, construction strategy, licensing pathway and financing needs differ. Any comparison should use vendor-independent cost and schedule assumptions and account for the entire delivered-power system.
Nuclear power does not require a Delaware reactor
Delaware is part of PJM, a regional transmission system with nuclear generation elsewhere in the footprint. A Delaware utility or cooperative could potentially contract for power or participate in a regional project, subject to procurement, regulatory, transmission and cost-allocation decisions. A general share of regional nuclear generation is not the same as a dedicated supply contract for Delaware customers.
Delaware Electric Cooperative identifies Old Dominion Electric Cooperative as its wholesale supplier and says its mix includes nuclear, coal, natural gas, landfill gas, wind and solar. This is a useful distinction between nuclear in a regional supply portfolio and nuclear generation physically located in the state.
Questions a serious proposal must answer
- Cost and financing: estimated overnight cost, financing rate, contingencies, escalation and who carries overruns.
- Schedule: design maturity, license review, construction milestones and supply-chain readiness.
- Site and water: flood exposure, geology, cooling options, water withdrawal and discharge, wetlands and emergency access.
- Safety and security: NRC licensing, emergency planning, physical security and independent oversight.
- Spent fuel: on-site storage, transport, federal disposal framework and long-term obligations.
- Grid connection: interconnection, transmission capacity, reserve requirements and local distribution upgrades.
- Ratepayer protection: who pays for feasibility, development, cancellation, decommissioning and long-term waste management.
- Community participation: local planning, public records, workforce, tax arrangements and meaningful consultation.
Keep the Indian River story separate
Indian River was a coal-fired generating station, not a nuclear facility. Its remaining 411-MW coal unit retired in February 2025. The former site has been discussed as one possible location for future energy reuse, but that does not make it a selected or approved nuclear site. The coal retirement and site-reuse questions are covered in a separate Indian River retirement briefing.
What to monitor next
- Any follow-on action by the General Assembly, DNREC, PSC or local governments.
- Published site-screening criteria or feasibility work.
- Utility procurement or regional nuclear offtake proposals.
- Formal developer announcements, land transactions or NRC applications.
- Independent cost comparisons with renewables, storage, gas, transmission and demand-side alternatives.
Sources & further reading
- SCR 18 — Nuclear Energy Feasibility Task ForceDelaware General Assembly · Task-force mandate
- Delaware Nuclear Energy Feasibility Task ForceDelaware General Assembly · Report receipt status
- Task force report: local government input needed as First State weighs future of nuclear energyDelaware Public Media · August 12, 2026
- About Delaware Electric CooperativeDEC · Wholesale supply portfolio
- Nuclear Energy InstituteIndustry background; consult NRC for regulatory determinations
- U.S. Nuclear Regulatory CommissionFederal reactor licensing and SMR information