Delaware uses more than one threshold in its 2026 data-center and large-energy-user laws. Those definitions serve different purposes. Treating them as interchangeable can misstate which projects are covered.
Large energy use facility
Thresholds in Title 30, § 2010, used by the large-energy-user regulatory framework.
Large-scale data center
100 MW or more, for the specific non-disclosure-agreement provisions in SB 312.
What counts as a large energy use facility?
Title 30, § 2010 defines a large energy use facility through three alternative tests:
| Test | Threshold | Meaning |
|---|---|---|
| High-utilization demand | 75 MW+ monthly maximum demand at a load factor of 85% or greater | A sustained, high-use load profile. |
| Instantaneous demand | 100 MW+ monthly maximum instantaneous demand | A high peak can qualify even without the 85% load-factor test. |
| Data-processing service | 30 MW+ monthly maximum demand | Applies when the facility is primarily engaged in NAICS 518210 services (data processing, hosting and related services). |
Multiple facilities may be aggregated if a utility or its regulatory body determines they pose reliability risks because of electricity use, proximity and operating characteristics. The statute lists factors such as proximity, common ownership or control, affiliates and shared local electrical infrastructure.
A separate 100-MW public-disclosure rule
SB 312 defines a “large-scale data center” as a data center that uses or is able to use 100 MW or more. It prohibits state agencies, counties and municipalities from entering into non-disclosure agreements that restrict public disclosure of information about potential or actual large-scale data center development.
This is a targeted restriction on government NDAs. It does not mean every project record is automatically public in every circumstance or erase other applicable confidentiality and public-records rules.
Which rules apply to which facilities?
- Title 26 § 203G / § 317: ESA, large-load tariff and cost allocation provisions apply to large energy use facilities served by Commission-regulated electric utilities.
- Title 29 § 8066: generation and clean-energy requirements for large energy use facilities.
- Title 9, 22 and 29 data-center NDA provisions: disclosure limits for government agreements involving 100-MW-plus large-scale data centers.
- Title 30 § 2010: shared large-energy-use-facility definition for specified business tax credit and related chapters.
Existing facilities operating as of August 26, 2026 are treated differently under § 203G(g), although a change that pushes an existing facility above the defined thresholds can trigger the ESA provisions. The statutory exception should be read carefully for expansions and changed uses.
Simple examples (illustrative only)
| Hypothetical facility | Threshold result | Why |
|---|---|---|
| 80 MW data center at 90% load factor | Likely meets first test | 75 MW+ and 85%+ load factor. |
| 105 MW instantaneous peak data center | Meets second test | 100 MW+ monthly maximum instantaneous demand. |
| 40 MW data-processing/hosting facility | May meet third test | Only if primarily engaged in NAICS 518210. |
| 60 MW industrial plant, 70% load factor | Not enough information to qualify under these tests | Would need to satisfy another statutory test or an aggregation rule. |
These examples simplify the law and are not legal determinations for actual projects.
Generation obligations before a large load connects
House Bill 445 added Title 29, § 8066. It is separate from the electric service agreement rules in Title 26. The generation provision generally requires a large energy use facility to produce or procure enough eligible generation to cover 100% of its annual energy needs. Qualifying resources must be connected in Delaware, the PJM Delmarva zone or a land-contiguous transmission zone with sufficient existing infrastructure to deliver the electricity into Delaware.
The statute identifies qualifying clean-energy technologies that include resources eligible under Delaware’s renewable portfolio standards, nuclear power and certain battery storage. It also permits combinations of on-site or directly interconnected generation, power-purchase agreements and other mechanisms approved by the relevant utility regulator. A single-cycle or open-cycle generating facility does not qualify under this section.
A ramp period is possible, but it has conditions
A facility that does not meet the full annual-energy requirement at the outset may seek approval for a plan to reach 100% within 10 years of commencing operations. During that period, it is subject to curtailment at specified price-impact thresholds and during reliability events, and it must participate in PJM demand-response programs. If it continues operating during curtailment periods, at least 50% of its backup power must be met by battery storage or clean-energy technology.
Minimum milestones before connection
| Requirement | Statutory threshold | Why it matters |
|---|---|---|
| Required generation | At least 25% energized and interconnected | A portion of the generation obligation must be real and connected before service begins. |
| Clean backup power | At least 25% energized and interconnected | Backup capacity cannot be treated only as a paper commitment. |
| Contract and financial assurance | 15-year binding agreement with a guaranteed insurance bond | Creates a contractual and financial backstop for specified failures to perform. |
The statute assigns the facility responsibility for seeking and funding new generation, in whole or in part. The precise compliance pathway, measurement, approved procurement and enforcement will depend on the law, regulatory review and the facility’s facts. This is not a blanket statement that every new data center is subject to identical requirements: first determine whether it meets the statutory definition, when it begins or changes operation, and which utility and regulator have jurisdiction.
Title 26’s ESA and transmission security provisions address service terms, cost allocation and financial risk for qualifying facilities served by a Commission-regulated utility. Title 29, § 8066 addresses the facility’s generation procurement, clean-energy and operating obligations. One does not replace the other.
Sources
- Title 30, § 2010 — definitions, including large energy use facilityDelaware Code Online · Current code
- Title 26, § 203G — electric service agreements for large energy use facilitiesDelaware Code Online · Current code
- Title 26, § 317 — rates for large energy use facilitiesDelaware Code Online · Current code
- Title 29, § 8066 — large energy use facilitiesDelaware Code Online · Current code
- SB 312 — bill detail and signed statusDelaware General Assembly · Signed August 26, 2026
- Title 29, § 8066 — Large energy use facilitiesDelaware Code Online · Current statute, § 8066
- Title 26, § 203G — Electric service agreements for large energy use facilitiesDelaware Code Online · Current statute, § 203G